The design of the future Celina Elementary School was completed in early 2023. The building, which includes a new 115,000-square-foot addition to the existing Celina Intermediate School, serves pre-kindergarten through 6th-grade students.
The addition is home to PK-3 students and is located west of the existing CIS building located on Portland Street. The 81,000-square-foot CIS has renovated and re-programmed as part of the building project and serve grades 4-6.
Construction of the new building addition of the Celina Elementary School has progressed well since breaking ground in October 2022. Abatement and demolition of the existing West Building will occur in the spring and summer of 2025, and all remaining site construction will be completed prior to the start of school in 2025.
Design of the future Celina High School is now complete. This new Celina High School building, which will serve grades 7-12, will be located on the existing Celina Primary School and Celina High School campus. The groundbreaking ceremony for the 7-12 building was held Nov. 25, 2024, and its anticipated opening date for students is the start of the 2027/2028 academic school year. Demolition of the existing Celina High School building will occur in the spring of 2027 and any final site construction will be completed in late spring / early summer of 2027.
The district is planning to repurpose the existing Middle School building to house the Mercer County Head Start program and the district offices. There also are plans to maintain the gymnasium and student dining spaces for extracurricular and athletic activities. Any renovation work associated with the existing Middle School would likely occur after the completion of the new Celina High School/Middle School building in late fall of 2027 / early winter of 2028.
Project Timeline
-
Celina Elementary School Building (PK-6)
Fall 2022 Early Site Package construction begins
Winter 2022/2023 Building design complete / contractor bidding
Spring 2023 Building Package construction begins
Summer 2024 Partial renovation of existing CIS Building (south)
Late Summer 2024 New Building Addition and partial renovation of existing CIS Building (south) completed for start of school in 2024/2025 school year
Fall 2024 Partial renovation of existing CIS Building (north)
Winter 2025 Partial renovation of existing CIS Building (north) construction complete
Spring / Summer 2025 Abatement and demolition of the existing West Building
Late Summer 2025 All remaining site construction complete
-
Celina High School Building (7-12)
Summer 2023 Site and building design to start
Spring 2024 Site design complete / contractor bidding
Early Summer 2024 Demolition of existing East Building
Summer 2024 Site construction begins
Late Summer 2024 Building design complete / contractor bidding
Fall 2024 Building construction begins
Early Spring 2027 Demolition of existing High School Building
Late Spring / Early Summer 2027 Final site construction completed
Fall 2027 Building construction completed for 2027/2028 school year